Start here
Gaiergy research, New York

New York Battery Incentives, Explained

Ten ways a New York battery can earn money. Which ones you get depends on size, place and program.

Hover over any acronym to see what it means. On a phone, tap it.

Battery yard with a battery, control cabinet and green transformer feeding a utility pole
LSRV
Locational System Relief Value
DRV
Demand Reduction Value
ICAP
Installed Capacity
LBMP
Location-Based Marginal Pricing
Size picks the route5 MW AC is the line
Solar unlocks E valueStandalone earns none
Place sets LSRVListed substations only
Standby can erase incomeCheck your rate class
Two routes, one battery

Size picks the road

Up to 5 MW AC, a battery sells to the utility under VDER. Over 5 MW, it sells wholesale to NYISO. The same megawatts cannot take both roads.

●Both roads: Federal ITC + NY property tax exemption (RPTL 487, unless the town opted out)
VDER road, up to 5 MW
LSRVBusy substation pay
DRVSummer peak window pay
ICAP (Alt 3)Capacity, passed through the utility
LBMPHourly day-ahead price
E value, if solar chargedClean energy pay
+ NYSERDA Retail IncentiveOne-time payment per kWh
A battery beside a road that splits: left to houses and a local substation, right to transmission towers
NYISO road, over 5 MW
LBMPPriced every 5 minutes
ICAP auctionCapacity, sold direct
Ancillary servicesRegulation and reserves
Index Storage CreditNYSERDA revenue floor
5.0 MW AC

VDER is capped at 5 MW AC; over 5 MW sells wholesale. Sources: utility VDER statements, NYSERDA program page, RPTL 487.

The VDER value stack

Watch one summer day pay

A 5 MW / 20 MWh battery charges at night and sends power out in the afternoon. Each value lights up only when it pays.

Charging, 5 hoursSending out, 4 hoursSending out in the DRV windowDRV window
Earned so far today, 5 MW / 20 MWh
$0
0% charged
12 am
Charging LBMP DRV
LBMP, sales minus charging cost$0
DRV, kWh in the window$0
LSRV: call days only (below) 
ICAP (Alt 3): one hour a year (below) 

Hot afternoon neighborhood with a sun and a battery feeding homes
What is DRV?

DRV: Demand Reduction Value

Paid per kWh the battery sends out in the summer peak window. No other hour pays DRV.

For new projects, DRV is a $/kWh rate in the window, locked for 10 years at the rate in effect when the project pays 25% of its interconnection cost. It is not a $/kW-year payment on the top 10 hours.

Sources: National Grid, NYSEG, RG&E, Con Edison, O&R, Central Hudson VDER statements and PSEG Long Island (LIPA Value Stack Statement No. 103) in effect October 15, 2026; PSC Order April 18, 2019, p.21. A DPS Staff proposal of December 11, 2025 would raise DRV and LSRV; the PSC has not ruled as of October 15, 2026.

Busy substation glowing warm with a battery beside it
What is LSRV?

LSRV: Locational System Relief Value

LSRV is extra pay for a battery at busy substations that each utility names. Each utility lists those substations, and how many MW of batteries it will still pay for at each one, in its monthly VDER statement.

Where LSRV pays today

Each utility caps the MW of batteries it will pay LSRV at each named substation. When a project locks in its rate, its MW come off the list. At zero, LSRV closes there.

A project locks its rate on its eligibility date, when it pays 25% of its interconnection cost, and keeps it for 10 years: PSC Order April 18, 2019, pp.17-18, 21.

MW left, by utility

Source: each utility's VDER Value Stack statement, published monthly (National Grid, NYSEG, RG&E, Con Edison, O&R, Central Hudson; LIPA: LSRV Statement No. 7, effective May 1, 2026). Last checked by Gaiergy: October 15, 2026. MW left changes every month. Check the latest statement before you plan.

At least 10 calls a year, 21 hours notice, 1 to 4 hours each, paid on the lowest hour of export, locked 10 years, no penalty for a miss: PSC Order April 18, 2019, pp.17-18. Rates and MW left: utility VDER statements in effect October 15, 2026 (National Grid, NYSEG, RG&E, Con Edison, O&R, Central Hudson, PSEG Long Island).

LSRV map

Every LSRV area with MW left

Tap a dot for the area, MW left, rate and source. Open a utility below for the full list.

Locations: National Grid, NYSEG and RG&E points matched by name to utility substation location files (Gaiergy NY substation dataset, September 2026). Hollow rings sit at the named town or neighborhood because no exact point was found. Basemap: Esri.

A faded gas peaker plant next to a glowing battery with a tall indigo pillar
Capacity under VDER

ICAP (Alt 3): one hour sets a year of pay

ICAP means Installed Capacity. New York pays power sources to stand ready for the year's highest demand. Under VDER, the utility passes this value to your battery through Alternative 3.

Why June 24, 2025?

It was New York's highest-demand hour of 2025: 31,857 MW, hour beginning 6 pm. What your battery sent out in that one hour sets its ICAP pay for every month of 2026.

Peak: NYISO June 2025 Operations Report (NYSRC); NYSEG lists it as "NYISO Top Ten Peak Hours", Hour 1: 06/24/25, 7:00 PM (hour ending): NYSEG VDER statement No. 110. Rule: "export during the New York Control Area peak of the previous calendar year": NYSEG Rule 40.B.6.c.

The kW resets each year at the new peak hour. The $/kW rate changes every month. Only DRV is locked for 10 years.

National Grid Rule 40, Leaf 220.3.1: pay = "the project's net kW injection during the ICAP Market Peak Hour in the previous year" times "the effective Alternative 3 Value Stack Capacity rate"; stand-alone storage "may only select Alternative 3" and gets Value Stack pay "for a term of 25 years from their interconnection date": National Grid PSC 220, Rule 40. DRV lock: PSC Order April 18, 2019, p.21.

The rate moves every month

NYSEG ICAP (Alt 3) rate, $ per kW-month, October 2025 to September 2026: low $2.08 (April 2026), high $8.43 (June 2026). NYSEG VDER statements No. 98 to 109.

Where the peak hour has landed

The peak has come between late June and late July. Run full power every hot weekday afternoon, June to August. Gaiergy view.

NYISO 2022 Peak Dates and Times; NYISO 2023 Peak Dates and Times; NYISO 2025 Final ICAP Forecast (2024 peak); NYISO June 2025 Operations Report.

When does my battery start getting ICAP pay?

Assumes the peak falls between June 20 and July 31, as the last four peaks did (Gaiergy assumption). First pay month follows NYSEG's "previous calendar year" wording. National Grid's tariff says "previous year", not "previous calendar year"; when its 12 months start is not confirmed.

Read the full ICAP Alt 3 explainer

What is the E value (the REC value)?

Clean energy pays. Grid energy does not.

The E value (environmental value) pays for clean energy sent to the grid. A battery earns it only on energy that came from its own renewable source.

Left: solar panels charge a battery, with a green leaf token. Right: a transmission tower charges a battery, with no token.
$0.03103 per kWh
$0 for a standalone battery

E value $0.03103 per kWh: utility VDER statements in effect October 15, 2026 (same rate at all six VDER utilities; LIPA pays no E value to stand-alone storage, LIPA tariff Leaf 34V). Standalone exclusion: National Grid Rule 40.

What sets itThe higher of the Tier 1 REC price or the social cost of carbon net of RGGI. Not confirmed against the 2017 VDER order.

2017 VDER Order, Case 15-E-0751 (secondary sources)

Standalone storage: excludedNational Grid Rule 40: stand-alone storage is "not eligible to receive the Environmental Component."

National Grid PSC 220, Rule 40

Hybrids: only clean kWhA battery paired with solar earns it only on energy shown to come from the renewable generator.

National Grid PSC 220, Rule 40

How much can my battery earn?

Build your battery's year

Pick a utility, a size and a place. The bar shows yearly revenue by stream, before costs.

Defaults: NYISO Zone F 2025 day-ahead. Sell price = average of each day's 4 best hours ($96.73); charge price = average of the 4 worst hours ($46.54). NYISO data. Long Island prices are Zone K, not Zone F. Edit for your zone.
Efficiency 85% is an Estimate. Installed cost is your own number; it is used for the ITC only.
Yearly revenue before costs
$0 Estimate

How we count
    NYSERDA Retail Storage Incentive

    A one-time incentive per kWh

    NYSERDA pays once, after the battery passes inspection. Your rate is the open block in your region.

    Open NYSERDA's Retail Storage program page

    ClosedInactiveOpen, filled share = money leftFuture

    Redrawn from NYSERDA's block dashboard, data as of October 6, 2026: NYSERDA Retail Storage block dashboard. Bar width = block MWh (block dollars / rate). Money left on closed blocks is leftover, not open funding. The NYC and Westchester split follows the block counts in the manual, pp.36-37 and 57.

    Descending clay staircase with a battery on a glowing step and coins

    How it pays

    1
    Lock your rateAt a complete application (manual p.15)
    2
    BuildPermission to operate by December 31, 2030 (pp.36-37)
    3
    Pass inspection and testInspection plus M&V
    4
    One payment, 100%At Completed status (p.69)

    Which kWh get paid

    Hours 1 to 4 at the full rate. Hours 5 and 6 at 25%. Nothing past 6 hours. Paid on at most 20 MWh.

    Full rate25% rateNot paid

    Incentive: Estimate

    Rules: Program Manual, April 2026, p.43. Rates: open blocks on the dashboard, October 6, 2026.

    Up to 5 MWProgram page
    Standalone battery on VDER is eligibleManual p.35
    Prevailing wage at 1 MW AC and upROS Block 5+, NYC 6+, Westchester 2+, pp.36, 41-42
    Operate by December 31, 2030pp.36-37
    Not with the Index Storage Credit or Bulk incentiveAlso not with an IOU dispatch-rights contract, IOU ownership, or an NWA contract signed on or before February 14, 2025. p.37
    Long Island: no Retail incentive nowp.20
    Inclusive Storage Incentive

    $350 per kWh

    One statewide block: $15.75 million (45 MWh). For behind-the-meter batteries at critical facilities in Disadvantaged Communities, or affordable housing. Not on Long Island. Opened April 13, 2026. Cannot combine with the market-rate incentive.

    NYSERDA webinar December 4, 2025, slide 14; manual pp.38-40, p.16.

    Stack builder

    What stacks on one battery?

    Pick a size, a charging source and a utility. Your battery fills with every payment it can earn. The red list shows what it cannot.

    Your battery

    Rules: utility VDER statements; NYSERDA manual pp.35, 37; National Grid PSC 220, Leaf 220.6; National Grid answer to Gaiergy, September 2026; Con Edison Rider T Guidelines 2026, section 6.7, p.21; National Grid Rule 40. Pairs with no clear rule show "Check the program rules".

    NYISO wholesale route, over 5 MW

    Three products, sold direct

    Over 5 MW AC, a battery sells energy, capacity and grid services straight into NYISO's wholesale markets.

    Battery yard

    LBMP

    Real-time price every 5 minutes. Day-ahead price every hour.

    NYISO Energy Market and Operational Data

    ICAP

    Capacity auctions, Rest of State, $ per kW-month:

    Capacity accreditation 2026/27: 4-hour battery 84.56% (CHPE in), 2-hour 64.65%.

    ICAP auction results (NYISO); NYISO ICAPWG, February 17, 2026.

    Ancillary services

    Regulation. 10-minute spinning reserve. 10-minute non-spinning reserve. 30-minute reserve.

    Index Storage Credit

    A NYSERDA contract that steadies wholesale revenue. How the credit works per secondary sources, not confirmed.

    NYSERDA tops upProject pays backStrikeIllustrative

    Round 1: 8 awards

    950 MW / 4,360 MWh

    Issued July 28, 2025 (ISCRFP25-1). Awards announced September 23, 2026. Monthly contract against a zonal reference price, up to 15 years for lithium-ion. Source is secondary; not confirmed on nyserda.ny.gov. Round 2 planned by the end of 2026, not confirmed. Not with NYSERDA Retail (manual p.37).

    Modo Energy articleNYSERDA solicitations page

    Modo Energy, September 23, 2026 (secondary); NYSERDA solicitations page.

    Federal ITC and NY tax

    Both roads keep these

    The federal Investment Tax Credit and the New York property tax exemption work on either road.

    Key rule

    No FEOC compliance, no tax credit.

    From 2026, a storage project must source at least 55% of its cost from non-FEOC suppliers (FEOC = Foreign Entity of Concern), or the federal ITC is lost.

    Sidley, The One Big Beautiful Bill Act, July 2025; also pv magazine. Not confirmed against the statute.

    Federal building with coin stacks and a battery

    Build the credit

    30%

    of eligible project cost

    Low-income bonus

    Low-income bonus is by competitive allocation; for a standalone battery it is not confirmed. 26 U.S. Code 48E.

    FEOC: a different percent

    Not part of the credit. It is a minimum share of the battery's cost that must come from non-FEOC sources. Miss it and the credit is zero.

    Storage: at least 55% non-FEOC cost share in 2026. Not confirmed against the statute.

    Sidley and pv magazine summaries.

    How long storage keeps it

    Start of construction year sets the share of the credit.

    100%Through 2033
    75%2034
    50%2035
    0%2036

    One Big Beautiful Bill Act, July 2025; 26 U.S. Code 48E.

    NY property tax: RPTL 487

    A 15-year exemption on the added value of a qualifying energy storage system. It applies unless the town, county or school district opted out by local law. The taxing body may require a PILOT within 60 days of the owner's notice.

    NY Tax Department, Assessor Manual, RPTL Section 487.

    Utility programs

    Extra pay from the utility

    Every New York utility pays batteries to cut load on hot days. Most ask you to give up DRV and LSRV in return. Read the rule before you enroll.

    Start here

    Which route fits my project?

    Three questions. The path lights up to your stack.

    1. How big is the battery?
    2. At a listed LSRV substation with MW left?
    3. Charged by new on-site solar?
    Sources

    Where every number comes from

      Compiled October 15, 2026.